Stage 1: Insurance.................................................$3,000.00 Temporary toilet........................................$2,000.00 Silt Fence.................................................$1,300.00 Install required entrance stabalized gravel for containment.............................................$1,600.00 Clearing trees & grubing,etc.........................$9,400.00 Engineering Stakeout..................................$3,900.00 Build 200 LF of 6 FT high-above grade block fence North Side Property..........................$13,000.00 Install 130 LF & 55 LF 12" Parking drain..........$8,000.00 Excavate footings, footing compaction...........$2,000.00 Some Electrical Rough - in temporary outlets..$2,000.00 Plumbing rough in under floor........................$4,077.00 Build foundation walls................................$12,400.00 Fill foundation walls....................................$8,150.00 Concrete floor.........................................$12,600.00 Supervision...............................................$1,500.00 STAGE 1 TOTAL.....................................$86,000.00
Stage 2:
Pacific Power CO, transformer......................$4,500.00 Framing with trusses.................................$13,000.00 Roofing....................................................$6,000.00 Install Store Front doors & windows.............$20,000.00 Exterior backer for porcelain tile....................$2,000.00 Procelain Exterior.......................................$5,353.00 Parking curbs with 6" base.........................$19,800.00 Installing 3 furnaces in trusses....................$26,243.00 Stucco with design....................................$7,700.00 Electrical rough in.....................................$10,000.00 plumbing rough in.......................................$6,000.00 site fill and grading.....................................$6,550.00 Supervision...............................................$2,500.00 STAGE 2 TOTAL...................................$130,246.00
Stage 3:
Street concrete work with water tap & 40 LF 2" copper pipe................................$8,200.00 Install Pretreatment oil-water seperator.........$4,600.00 Install 18" street storm line with box..............$9,900.00 Replace 120 LF sidewalk & curb on street.....$10,500.00 Site grading work.......................................$4,500.00 Install rubbish slab with 6:high walls..............$1,800.00 Rusbbish walls & gate.................................$2,263.09 Aluminum color facia with soffit....................$3,500.00 Aluminum color facia with soffit....................$3,106.00 Sidewalks-building 5"x9', 5 x 180 LF with 6" base & 9'x18' handicap ramp.................................$10,000.00 Electrical rough in also safety plates............$19,000.00 Plumbing rough in.......................................$5,000.00 HVAC.......................................................$8,747.00 4" Sanitary & Grease trap............................$6,700.00 Insulation walls & ceiling with Sunroc blown in above......................................................$5,974.22 Drywall 5/8" fire rated in kitchen & gypsum.....$3,397.00 Painting...................................................$3,298.00 STAGE 3 TOTAL...................................$110,485.31
Stage 4:
Interior wood frames & doors with hardware....$9,207.40 Interior base & casings..................................$900.00 Control cabinet..........................................$2,000.00 Pulpit.......................................................$1,250.00 Kitchen cupboards.....................................$6,336.00 Flooring-ceramic, vinyl & carpet..................$11,845.00 Bath assessories & bath partitions, extinguishers, roll-up door...........................$2,400.00 Sprinkling lin to island....................................$400.00 Plumbing fixtures........................................$6,000.00 Electrical................................................$20,000.00 Sign...........................................................$800.00 4 Extinguishers cabinets and rollup door.........$1,167.00 Site work grading.........................................$500.00 3" Asphalt...............................................$31,000.00 Striping......................................................$300.00 Supervision...............................................$2,500.00 STAGE 4 TOTAL.....................................$97,105.40
Stage 5: Landscaping............................................$10,000.00 Sprinkling..................................................$5000.00 STAGE 5 TOTAL.....................................$15,000.00 |